[cs_content][cs_element_section _id=”1″ ][cs_element_row _id=”2″ ][cs_element_column _id=”3″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;”] December 2018[/x_custom_headline][cs_text class=”less_faded” style=”border:#002868 solid 2px;font-size:18px;padding:24px;color:#002868;”]At the December 3, 2018, School Board Work Session, Crabtree, Rohrbaugh & Associates presented a Middle School Update and a Review of Construction Bids for the project. The Board voted at this meeting to award the Middle School Construction Project to five bidders based on their low Base Bids for a total bid cost of $44,702,949.[/cs_text][cs_element_gap _id=”6″ ][cs_text class=”cs-ta-center less_faded” style=”border:#002868 solid 2px;font-size:18px;padding:24px;color:#002868;”]
• Contents •
Project Schedule
Bid Summary
Estimate & Bid Comparison
[/cs_text][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”13″ ][cs_element_row _id=”14″ ][cs_element_column _id=”15″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;margin-top: 0px;”] Project Schedule[/x_custom_headline][cs_text class=”faded” style=”font-size:24px;border:#002868 solid 2px;”]
Bid Schedule – Middle School Project |
|
---|---|
September 13, 2018 | Board Review of Building CD Phase |
September 20, 2018 | Board Approval of Building CD Phase: Release of Bids |
September 21, 2018 | Bid Release for Building Construction (5 week bid period) |
November 20, 2018 | Bid Opening |
December 3, 2018 | Board Approval: Award of Contract |
December 4, 2018 | Issue Notice of Intent to Award Contracts |
December 18, 2018 | Issue Notice to Proceed |
April 1, 2019 | Building Pad Turnover to Contractors |
May 1, 2021 | Building Turnover to Owner for Move-in |
July 16, 2021 | Building Substantial Completion |
August 2021 | Students in New Middle School |
June 2022 | Site Work Substantial Completion |
[/cs_text][/cs_element_column][/cs_element_row][cs_element_row _id=”23″ ][cs_element_column _id=”24″ ] [/cs_element_column][/cs_element_row][cs_element_row _id=”30″ ][cs_element_column _id=”31″ ][cs_element_gap _id=”32″ ][x_button shape=”square” size=”global” block=”true” circle=”false” icon_only=”false” href=”#toc” title=”Return to Table of Contents” target=”” info=”none” info_place=”top” info_trigger=”hover” info_content=””] Return to Table of Contents[/x_button][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”39″ ][cs_element_row _id=”40″ ][cs_element_column _id=”41″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;margin-top: 0px;”] Bid Summary[/x_custom_headline][/cs_element_column][/cs_element_row][cs_element_row _id=”48″ ][cs_element_column _id=”49″ ][cs_text _order=”0″ class=”faded” style=”font-size:18px;border:#002868 solid 2px;”]
Manheim Township Middle School Bid Summary | |||
Base Bid Results | $43,674,949 | ||
Site Construction | $7,733,031 | ||
Total | $51,407,980 | ||
100% CD Estimate at ACT 34 Hearing | $53,410,219 | ||
Base Bid Difference between Estimate | ($2,002,239) | ||
General Construction – eci Construction | Base Bid | $26,889,000 | |
Alt. GC-1 Roof Top Screen Walls | Add | $0 | |
Alt. GC-2 EPDM Roofing – 30 Year Warranty | Add | $274,000 | |
Alt. GC-3 Bridge | Deduct | $0 | |
Alt. GC-4 Terrazzo Flooring | Add | $0 | |
Alt. GC-5 Porcelain Tile Flooring | Add | $604,000 | |
Alt. GC-6 Porcelain Tile Flooring with Bridge | Deduct | $0 | |
Alt. GC-7 Porcelain Tile Flooring without Bridge | Deduct | $0 | |
Alt. GC-8 Aluminum Sun Shades | Add | $60,000 | |
Alt. GC-9 Subgrade Excavation | Add | $0 | |
Alt. GC-10 Aluminum Windows | Add/Deduct | $0 | |
Alt. GC-11 Fence Piers | Add | $34,000 | |
Alt. GC-12 Powder Coated Guardrails & Stringers | Add | $86,000 | |
Alt. GC-13 Powder Coated Guardrails & Stringers w/o Bridge | Add | $0 | |
GC Subtotal | $27,947,000 | ||
HVAC Construction – Matchline Mechanical | Base Bid | $7,742,000 | |
Alt. HC-1 Gas Boiler | Add/Deduct | -$30,000 | |
HVAC Subtotal | $7,712,000 | ||
Plumbing Construction – SM Fridy Mechanical | Base Bid | $1,744,949 | |
No Alternatesr | $0 | ||
PC Subtotal | $1,744,949 | ||
Fire Protection – VFP Fire Systems | Base Bid | $710,000 | |
No Alternates | $0 | ||
FP Subtotal | $710,000 | ||
Electrical Construction – Farfield Inc. | Base Bid | $6,589,000 | |
Alt. EC-1 Aluminum Feeders | |||
EC Subtotal | $6,589,000 | ||
Construction Total | $44,702,949 |
[/cs_text][/cs_element_column][/cs_element_row][cs_element_row _id=”56″ ][cs_element_column _id=”57″ ][cs_element_gap _id=”58″ ][x_button shape=”square” size=”global” block=”true” circle=”false” icon_only=”false” href=”#toc” title=”Return to Table of Contents” target=”” info=”none” info_place=”top” info_trigger=”hover” info_content=””] Return to Table of Contents[/x_button][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”65″ ][cs_element_row _id=”66″ ][cs_element_column _id=”67″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;margin-top: 0px;”] Estimate & Bid Comparison[/x_custom_headline][/cs_element_column][/cs_element_row][cs_element_row _id=”74″ ][cs_element_column _id=”75″ ][cs_text _order=”0″ class=”faded” style=”font-size:24px;border:#002868 solid 2px;”]
Construction Costs | CRA 100% SD Estimate |
Base Bid With Alternates |
1. General Construction | $30,420,219 | $27,947,000 |
2. HVAC Construction | $7,200,000 | $7,712,000 |
3. Plumbing Construction | $3,360,000 | $1,744,949 |
4. Fire Protection | included in PC | $710,000 |
5. Electrical Construction | $6,480,000 | $6,589,000 |
Subtotal | $47,460,219 | $44,702,949 |
6. Site Construction | $5,950,000 | $7,733,031 |
Construction Subtotal | $53,410,219 | $52,435,980 |
Under Budget by ($974,239) |
[/cs_text][cs_element_gap _id=”77″ ][cs_text class=”faded” style=”font-size:24px;border:#002868 solid 2px;”]
Construction Related Soft Costs | CRA 100% SD Estimate |
CRA Base Bid With Alternates |
7. Construction Contingency | $2,170,918 | $2,261,799 |
8. Testing & Inspections | $949,777 | $128,774 |
9. Permitting Fee | $592,730 | $551,232 |
10. Asbestos Abatement | $862,736 | $331,495 |
Subtotal | $4,576,160 | $3,633,495 |
Total Construction Costs | $57,986,379 | $56,069,475 |
Under Budget by ($1,916,904) |
[/cs_text][cs_element_gap _id=”79″ ][cs_text class=”faded” style=”font-size:24px;border:#002868 solid 2px;”]
Soft Costs | ||
11. Basic Services, Financing, Clerk of the Works |
$4,317,221 | $4,301,242 |
12. F.F.&E. | $2,606,400 | $2,606,400 |
Subtotal | $6,923,621 | $6,907,642 |
Total Costs | $64,910,000 | $62,977,117 |
Under Budget by ($1,932,884) |
[/cs_text][/cs_element_column][/cs_element_row][cs_element_row _id=”86″ ][cs_element_column _id=”87″ ][cs_element_gap _id=”88″ ][x_button shape=”square” size=”global” block=”true” circle=”false” icon_only=”false” href=”#toc” title=”Return to Table of Contents” target=”” info=”none” info_place=”top” info_trigger=”hover” info_content=””] Return to Table of Contents[/x_button][/cs_element_column][/cs_element_row][/cs_element_section][cs_element_section _id=”95″ ][cs_element_row _id=”96″ ][cs_element_column _id=”97″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;margin-top: 0px;”] Building Animation[/x_custom_headline][/cs_element_column][/cs_element_row][cs_element_row _id=”104″ ][cs_element_column _id=”105″ ] [/cs_element_column][/cs_element_row][cs_element_row _id=”111″ ][cs_element_column _id=”112″ ][x_button shape=”square” size=”global” block=”true” circle=”false” icon_only=”false” href=”#toc” title=”Return to Table of Contents” target=”” info=”none” info_place=”top” info_trigger=”hover” info_content=””] Return to Table of Contents[/x_button][/cs_element_column][/cs_element_row][/cs_element_section][/cs_content]