February 2018
At the January 18, 2018 School Board Meeting, the architect indicated that they are currently at the completion of the Design Development phase and are ready to move into the Construction Document phase. Below is a list of the current recommendations and forthcoming recommendations per phase:
- Approve the Design Development Phase and authorize Crabtree Rohrbaugh and Associates to proceed to the Construction Document phase. (February)
- Approve the Construction Document Phase and authorize Crabtree Rohrbaugh and Associates to bid the Middle School Project. (June)
- Approve the award of contracts to begin construction of the Middle School Project. (July)
Based on the project update presented at the January 18, Board Meeting, the School Board approved the Design Development phase for the Middle School Project and authorized Crabtree Rohrbaugh and Associates to proceed to the Construction Document phase at the February 8 School Board Work Session.
Schematic Design
Design Development – Site Plan
Project Update:
- North-end Parent Drop-Off
- Eliminate existing North Parking – new parking total
- Multi-Purpose Field
- Storm Water Management Plan
- Grading Plan
- Loading Dock/Service Area
Design Development – Floor Plans
Project Update:
- Finalized Floor Plan
- Third-party Code Review
- Completed Interior layouts & meetings with Faculty
- Continued Food Service design meetings
- Placement of roof-top mechanical equipment & utility runs
Design Development – Floor Plans
Next Steps:
- Structural column grid
- Exterior & Interior material selection
- Color Scheme & Wayfinding design
- Fixed casework design
- Ceiling and lighting fixture layouts
- Food Service equipment layouts
- Black Box Seating
- Courtyard design
- Coordination of MEP Systems