February 2021
Project Achievements
Site
- Spread Topsoil along west elevation
- Prepared area in front of loading dock for concrete (next week weather permitting)
- Began laying out for sidewalks along south elevation
GC
- Completed installing ceramic floor tile in area F corridors & started in area E
- Began grinding/polishing terrazzo in serving area
Plumber
- Continued setting toilets and sinks throughout the facility
Electrician
- Finished installing lights in the corridors
- Continued to terminate data wiring in IDF rooms
- Continued installing outlets and switches throughout the facility
Mechanical
- Started up the boilers and roof top HVAC units
Sprinkler
- Continued installing sprinkler heads in ceiling tile as grid is being installed
Project Goals (for next month)
- Complete ceiling tile installation in areas D, E & F
- Complete first floor tile installation
- Begin the installation of food service equipment
- Start-up the permanent heating system in areas D, E and F
- Pour concrete pad at loading dock
- Pour concrete walks along the access drive (west elevation)
- Begin carpet installation
- Begin interior door installation