January 2018
Project Schedule
Project Schedule - Design Phase |
|
---|---|
May - June 2017 | Programming/Preliminary Design |
July - September 2017 | Schematic Design - "Exploration" Board Action Required: Adopt Maximum Building Construction Cost in preparation for Act 34 Public Hearing held on October 10, 2017 |
October 2017 - February 2018 | Design Development - "Refinement" |
February - June 2018 | Construction Documents - "Preparation" Board Action Required: Approve Project to be released for Bidding |
Note: Schedule is pending Municipal and Regulatory Agency Approvals |
Project Schedule - Land Development Plan |
|
---|---|
January 31, 2018 | Submit LD Plans to Manheim Twp. Submit NPDES Plans to Lancaster Co. Conservation |
February 21, 2018 | Manheim Twp. Planning Commission Meeting |
March 21, 2018 | Manheim Twp. Planning Commission Meeting |
May 22, 2018 | Township Board of Commissioners Conditional Approval |
June 2018 | Record Plans |
Schedule - High School & Landis Run Projects
Schematic Design
Design Development - Site Plan
Project Update:
- North-end Parent Drop-Off
- Eliminate existing North Parking - new parking total
- Multi-Purpose Field
- Storm Water Management Plan
- Grading Plan
- Loading Dock/Service Area
Design Development - Floor Plans
Project Update:
- Finalized Floor Plan
- Third-party Code Review
- Completed Interior layouts & meetings with Faculty
- Continued Food Service design meetings
- Placement of roof-top mechanical equipment & utility runs
Manheim Township School District
Design Development - Floor Plans
Floor Plan
The Manheim Township School District asserts that this document is exempt from public disclosure consistent with Section 708(b)(3) of the Right-to-Know Law, 65 P.S. § 67.708(b)(3). Any public disclosure of this record would create a reasonable likelihood of endangering the safety and physical security of a School District building, particularly since this record includes building plans that could expose or create a vulnerability. In the event that PDE receives a public records request for this document, the School District requests that PDE notify the School District immediately and allow the School District the opportunity to participate as an interested third party.
Design Development - Floor Plans
Next Steps:
- Structural column grid
- Exterior & Interior material selection
- Color Scheme & Wayfinding design
- Fixed casework design
- Ceiling and lighting fixture layouts
- Food Service equipment layouts
- Black Box Seating
- Courtyard design
- Coordination of MEP Systems
Manheim Township School District
Design Development - Floor Plans
Floor Plan
The Manheim Township School District asserts that this document is exempt from public disclosure consistent with Section 708(b)(3) of the Right-to-Know Law, 65 P.S. § 67.708(b)(3). Any public disclosure of this record would create a reasonable likelihood of endangering the safety and physical security of a School District building, particularly since this record includes building plans that could expose or create a vulnerability. In the event that PDE receives a public records request for this document, the School District requests that PDE notify the School District immediately and allow the School District the opportunity to participate as an interested third party.
Exterior Renderings


Interior Renderings