June 2018
At the June 14, 2018, School Board Work Session, Mr. Anthony Colestock from Crabtree, Rohrbaugh & Associates provided an update on the design phase and timeline for the Middle School Construction project.
Project Schedule
Project Schedule - Land Development |
|
---|---|
January 31, 2018 | Submit LD Plans to Manheim Twp. Submit NPDES Plans to Lancaster Co. Conservation |
February 21, 2018 | Manheim Twp. Planning Commission Meeting |
April 18, 2018 | Manheim Twp. Planning Commission Meeting |
July 9, 2018 | Township Board of Commissioners Conditional Approval |
June 2018 | Record Plans |
Bid Schedule - North Site Project |
|
---|---|
June 14, 2018 | Board Review of Site CD Phase |
June 21, 2018 | Board Approval of Site CD Phase: Release of Bids |
June 28, 2018 | Bid Release for North Site Construction (5 week bid period) |
August 2, 2018 | Bid Opening |
August 9, 2018 | Board Approval: Award of Contract @ Work Session |
Return to Table of Contents
Site Construction

Construction Site Plan: June 2018
Site Estimate |
||
---|---|---|
ESTIMATED COSTS | LOW | HIGH |
Site Construction | $8,619,248 | $9,409,754 |
Return to Table of Contents