May 2018
At the May 10, 2018, School Board Work Session, Mr. Anthony Colestock from Crabtree, Rohrbaugh & Associates provided an update on the design phase and timeline for the Middle School Construction project.
This presentation also included 3-D renderings of the exterior design of the school.
Project Schedule
Project Schedule - Land Development |
|
---|---|
January 31, 2018 | Submit LD Plans to Manheim Twp. Submit NPDES Plans to Lancaster Co. Conservation |
February 21, 2018 | Manheim Twp. Planning Commission Meeting |
April 18, 2018 | Manheim Twp. Planning Commission Meeting |
June 11, 2018 | Township Board of Commissioners Conditional Approval |
June 2018 | Record Plans |
Bid Schedule - GC & MEP Contracts |
|
---|---|
September 13, 2018 | Board Review of Building CD Phase |
September 20, 2018 | Board Approval of Building CD Phase: Release of Bids |
September 27, 2018 | Bid Release for Building Construction (5 week bid period) |
November 1, 2018 | Bid Opening |
November 8, 2018 | Board Approval: Award Contracts @ Work Session |
November 12, 2018 | Pre-Construction Meeting: Contractors Mobilize |
Bid Schedule - North Site Project |
|
---|---|
June 14, 2018 | Board Review of Site CD Phase |
June 21, 2018 | Board Approval of Site CD Phase: Release of Bids |
June 28, 2018 | Bid Release for North Site Construction (5 week bid period) |
August 2, 2018 | Bid Opening |
August 9, 2018 | Board Approval: Award of Contract @ Work Session |
Return to Table of Contents
Exterior Renderings

May 2018 Construction Update: Site Plan

May 2018 Construction Update: Main Entrance

May 2018 Construction Update: Outdoor Classroom

May 2018 Construction Update: 8th Grade Wing

May 2018 Construction Update: 7th Grade Wing

May 2018 Construction Update: Courtyard

May 2018 Construction Update: Cafeteria/Courtyard