[cs_content][cs_element_section _id=”1″ ][cs_element_row _id=”2″ ][cs_element_column _id=”3″ ][x_custom_headline level=”h1″ looks_like=”h1″ accent=”false” class=”cs-ta-center faded” style=”border:#002868 solid 2px;”] November 2018[/x_custom_headline][cs_text class=”less_faded” style=”border:#002868 solid 2px;font-size:18px;padding:24px;color:#002868;”]At the November 8th School Board Work Session, Jay Darkey from JPD Architects, LLC, reviewed the project bid timeline with the members of the School Board.[/cs_text][cs_text class=”faded” style=”font-size:24px;border:#002868 solid 2px;margin-top:24px;”]
Bid Schedule – Middle School Project |
|
---|---|
September 21, 2018 | Bid Release for Building Construction |
November 20, 2018 | Bid Opening |
December 3, 2018 | Board Approval: Award of Contract |
December 2018 | Issue Notice to Proceed |
April 1, 2019 | Building Pad Turnover: Contractors Mobilize On-Site |
July 16, 2021 | Building Substantial Completion |
December 30, 2021 | Site Substantial Completion |
[/cs_text][cs_element_global_block _id=”7″ ][/cs_element_column][/cs_element_row][/cs_element_section][/cs_content]